What is a construction change order?

A construction change order documents an agreed change to the work. It typically describes the revised scope and records any agreed adjustment to price, schedule, or both. The steps and approval roles vary by project, so use the project’s own documents and procedures to identify who reviews and authorizes a change.

A change may start with an owner request, a design revision, or a condition the team discovers in the field. Keep the original request and the approved record easy to distinguish. A cost proposal describes what a change could cost; the change log should show whether it is still under review or has been approved.

How a change order differs from an RFI or daily report

A request for information (RFI) asks for clarification. A daily report records what happened on site. Either can help explain why a change was considered, but the change order has a different job: recording the agreed adjustment through the project’s change process.

For example, a daily report may note that a crew could not proceed in one room because a revised detail was pending. An RFI may clarify the detail. If the clarification leads to a proposed change in scope, cost, or time, track that proposal separately and cross-reference the supporting records.

The construction change order process, step by step

Use the project’s workflow and assigned reviewers. A practical tracking sequence looks like this:

  • Identify the trigger and record the affected drawing, location, and original scope.
  • Describe the proposed change in terms of what will be added, removed, or revised.
  • Gather trade pricing and supporting quantities. Identify allowances, exclusions, and any credits.
  • Ask the scheduler or field team to evaluate affected activities, procurement dates, and trade handoffs.
  • Route the proposal for review and track its status, owner, and next action.
  • After the required approvals, communicate the decision and update the relevant budget, schedule, and field records.

Worked example: moving a partition during an office renovation

Imagine the owner requests that a conference room partition move two feet. The project engineer identifies the rooms and drawing revisions. The estimator checks the added and removed framing quantities and asks the electrical trade whether outlets are affected. The superintendent checks whether the revised layout conflicts with work already scheduled.

Suppose the illustrative proposal includes $2,400 in added framing and finish work, a $600 credit for work removed, and $900 for electrical revisions. The net proposed cost is $2,700 before any other applicable adjustments. Keep those line items visible so reviewers can see how the total was calculated.

If the electrical work needs an extra day, check whether it can fit within the existing sequence before claiming the project finish date will move. Document the schedule assessment separately from the cost estimate. Once the decision is approved through the project’s process, communicate the revised scope and the agreed cost and time adjustments.

What to include in a construction change order log

Give each item an identifier and a short description. Record when it was raised, who owns the next step, the affected area, proposed cost, schedule impact or open schedule questions, current status, and links to the supporting documents. Keep proposed and approved amounts distinguishable.

Review aging items before project meetings. Prioritize the decisions that could hold up ordering or installation. When an item closes, record the outcome and link the accepted documentation so the team can trace it later.

How to show change order experience in a construction interview

Project engineers may assemble records and maintain logs. Estimators may check quantities and pricing. Superintendents may explain field and sequencing impacts, while project managers may coordinate review. The split varies by employer, so describe the work you personally handled.

Prepare one example that explains what triggered the change, how you checked the original scope, what you documented, and who made the final decision. An illustrative resume bullet is: “Maintained the change log for a commercial renovation and reconciled trade proposals against revised drawings before project-manager review.” Use it only as a model for your actual work.